Euclid Corridor Design Review Case Report
EUCLID 3 STUDENT HOUSING
Return to Case List | Start Over
| Print Report (PDF format)
Project Information
Euclid Corridor Case # EC 2018-042
| Address: | 11601 Euclid Avenue |
| Company: | RDL Architects |
| Architect: | RDL Architects / PrideOne Construction |
| Description: | |
| Notes: | |
Committee Actions/Submissions
| Date: | November 8, 2018 |
| Committee: | Staff |
| Action Type: | Initial Plan Submission |
| Conditions/Notes: | |
| Date: | November 15, 2018 |
| Committee: | Local Design Review Committee |
| Action Type: | Approved with Conditions |
| Conditions: | |
Schematic approval provided with conditions: 1) Restudy the surface paving treatement at corner of building ( E 115th & Euclid) 2) Study improving the massing of the corner element - looks awkward 3) Reduce drop-off length - currently 65 feet 4) Materiality of building should be simplilfie - revisit element of brick w/storefront glazing 5) Study courtyard entrance and functionality |
|
| Date: | November 16, 2018 |
| Committee: | City Planning Commission |
| Action Type: | Conceptual Approval |
| Conditions: | |
| Date: | December 13, 2018 |
| Committee: | Staff |
| Action Type: | Revised Plan Submission |
| Conditions/Notes: | |
| Date: | December 20, 2018 |
| Committee: | Local Design Review Committee |
| Action Type: | Approved with Conditions |
| Conditions: | |
Conditions: 1) Study corner element and tie landscape or pavement treatment to building elements. 2) Include enhanced signage at courtyard entrance. |
|
| Date: | December 21, 2018 |
| Committee: | City Planning Commission |
| Action Type: | Approved |
| Conditions: | |